Manufacturers in England, Scotland and Wales have until 11:59pm on 30 November to apply for electricity-cost relief under the British Industrial Competitiveness Scheme. The government opened the first application window on 1 October 2026, with decisions due in early 2027 and the first exemptions scheduled to begin in April next year.

The scheme is intended for eligible manufacturers in growth industries and the foundational industries that supply them. The Department for Business, Innovation, Science and Trade says it could reduce costs by up to £40 per megawatt hour for qualifying businesses. The government has separately said more than 10,000 manufacturers could benefit, with potential reductions of up to 25% in eligible electricity bills. Neither figure is a guaranteed saving for every applicant.

Which charges are being removed

The relief concerns indirect electricity policy costs, rather than a blanket discount on all power. From April 2027, eligible businesses are due to be exempt from the indirect costs of the Renewables Obligation and Feed-in Tariffs. An exemption from Capacity Market costs is scheduled to start in October 2027. These dates appear in the government's business guidance for the first year of the scheme.

The distinctions matter for companies budgeting for the year ahead. The underlying price of electricity is not being abolished. A factory may still face wholesale energy costs and other charges even if it qualifies for relief on these specified policy costs. The stated reductions concern qualifying electricity use and can vary depending on the business's actual bills and circumstances.

The government's collection page says the scheme applies to businesses registered with Companies House, operating in eligible sectors and manufacturing eligible products. It uses Standard Industrial Classification codes for sectors and Harmonised System codes for products, alongside a minimum electricity-use requirement. A company cannot assume that a product is covered simply because manufacturing is its main business; it needs to check the published eligibility list and its own electricity data.

What companies must establish before applying

The department has published an online eligibility checker intended to help companies assess whether they are likely to qualify. It has also published applicant guidance, examples of free-text statements, evidence requirements and specific guidance for landlords and other third parties. An eligibility check is a preliminary indication, not the formal decision on an application.

The official guidance tells applicants to prepare company identification, evidence about the qualifying activity and information about electricity use. It also covers the calculation of relief where a site carries out both eligible and ineligible production. In that case, an applicant cannot treat all its electricity as eligible without accounting for the non-qualifying activity taking place at the site.

Shared meters and sub-metering have their own rules in the guidance, as do situations in which a landlord or another party is involved in the supply arrangement. The department's update published on 1 October clarified how ineligible on-site activity should be included when businesses calculate their qualifying proportion. A further update on 2 October clarified how the product codes should be read against the UK Tariff. These changes are relevant to applicants preparing evidence close to the deadline.

The timetable and what follows a decision

Businesses have a two-month first-year application window, from 1 October to the end of 30 November 2026. According to the official guidance, eligibility decisions are expected in early 2027. The government does not say that all qualifying businesses will see an immediate reduction as soon as they submit the form: the first policy-cost exemption is scheduled for April and the Capacity Market exemption for October.

The department's guidance also explains how appeals work and sets out ongoing obligations after support is awarded. It notes that decisions will be paused over the Christmas period, from 21 December 2026 to 4 January 2027. Applicants should distinguish between confirmation that they are eligible and the eventual level of exemption shown through electricity suppliers.

The scheme is also designed to avoid duplicating relief already received through the British Industry Supercharger, a separate arrangement for energy-intensive industry. Companies that already receive support should check how the schemes interact instead of assuming that the same unit of electricity can receive both benefits. The latest government guidance is the authoritative source for those calculations.

For manufacturers, the immediate development is the opening of applications, not a reduction already appearing on electricity bills. The £40-per-megawatt-hour and 25% figures describe possible upper-end benefits for eligible businesses, while actual decisions and charges will depend on evidence, qualifying consumption and the phased dates in 2027.